A technology company has begun construction on a new data center campus. The project, part of a large-scale expansion, requires a highly reliable, secure, and scalable electrical infrastructure to support mission-critical operations.
Romanoff Industries, an MCE company, has partnered with a regional electrical contractor to supply medium-voltage pad-mounted transformers and medium-voltage switchgear to support the facility’s power distribution system.
The Challenge
Data centers are among the fastest-growing infrastructure segments in the U.S., projected to grow in double digits over the next 10 years, driven in part by the rise of AI computing. Energy consumption by data centers is rising sharply, as a result. Utilities are also growing in response.
Large-scale data center projects demand:
- Secure, domestically manufactured electrical components
- Adherence to detailed specifications
- Sectionalized power distribution for phased buildouts
- Rapid turnaround to maintain aggressive construction schedules
In this case, the project requires configured transformers and switchgear assemblies built to specifications. Modifications include specific grounding locations, lockbox positioning, sectional shutdown capabilities, and other detailed design elements to align with the facility’s standardized build model and security requirements.
Speed was also critical. Once the formal purchase order was issued, equipment needed to be delivered in under 60 days to avoid impacting the construction timeline.
The Solution
Romanoff served as the technical and logistical bridge between the contractor and manufacturing partner, Maddox. The team was able to:
- Secure priority pricing
- Coordinate modifications to meet specifications
- Ensure all equipment met security requirements
- Oversee order accuracy and documentation
- Accelerate production and shipment timelines
While the electrical equipment itself is standardized to meet national efficiency requirements, the project’s customization and coordination requirements demanded proactive communication and rigorous specification management.
The Result
MCE’s team ensured that every technical detail was accounted for and that equipment arrived on time from Maddox.
The transformers and switchgear were scheduled to ship in less than 60 days from purchase order issuance, helping the contractor maintain its schedule. All equipment was built in the U.S. to meet security requirements and configured to support phased power activation as the facility continues to expand.
By combining supplier relationships, detailed specification management, and responsive coordination, MCE delivered a competitive, fast-turn solution for a complex data center project, reinforcing our ability to support large-scale power infrastructure initiatives in a fast-growing market.